NJ Windmill Projects Sink as Ørsted Ceases Development of Ocean Wind 1 and Ocean Wind 2; Govenor Murphy Calls Move Outrageous – MidJersey.News

April 24, 2024 maximios News

Congressman Jeff Van Drew stated “I am thrilled to see that Orsted has decided to pack up its offshore wind scam and leave South Jersey’s beautiful coasts alone. A tremendous win for South Jersey residents, our fisherman, and the historic coastline of the Jersey shore.”

October 31, 2023

In a press release today from Ørsted, the Board of Directors has decided to cease the development of U.S. Offshore Projects, Ocean Wind 1 and Ocean Wind 2. Govenor Phil Murphy called today’s decision by Orsted to abandon its commitments to New Jersey outrageous and calls into question the company’s credibility and competence. (see full statement below)

“Due to adverse impacts relating to supply chain delays, increased interest rates, and the lack of an OREC adjustment on Sunrise Wind, we have recognized impairment losses of DKK 28.4 billion in 9M 2023. The majority of these (DKK 19.9 billion) relates to our US offshore project Ocean Wind 1.

Net profit amounted to DKK -19.9 billion, and return on capital employed (ROCE) came in at -14 %. Net profit and ROCE excluding impairment losses amounted to DKK 8.5 billion and 13 %, respectively.

Our previously guided EBITDA for 2023, excluding new partnership agreements, of DKK 20-23 billion remains unchanged, when excluding a provision of approximately DKK 8-11 billion related to potential cancellation fees following our decision to cease the development of Ocean Wind 1. Due to a later timing across our project portfolio and the termination of investments on Ocean Wind 1, our gross investment for 2023 is now expected to amount to DKK 40-44 billion, a reduction of DKK 4 billion.“

“Therefore, as part of our ongoing review of our US offshore wind portfolio, we’ve decided to cease the development of Ocean Wind 1 and Ocean Wind 2. At the same time, we’ve taken final investment decision on the 704 MW Revolution Wind project, progressing it to the construction phase with an attractive forward-looking value creation.“

Congressman Jeff Van Drew stated “I am thrilled to see that Orsted has decided to pack up its offshore wind scam and leave South Jersey’s beautiful coasts alone. A tremendous win for South Jersey residents, our fisherman, and the historic coastline of the Jersey shore.”

I am thrilled to see that Orsted has decided to pack up its offshore wind scam and leave South Jersey’s beautiful coasts alone.

A tremendous win for South Jersey residents, our fisherman, and the historic coastline of the Jersey shore. https://t.co/k36MY8EOfM

— Congressman Jeff Van Drew (@Congressman_JVD) November 1, 2023

Govenor’s Office File Photo

New Jersey Govenor Phil Murphy released the following statement about Ørsted’s decision:

“Today’s decision by Orsted to abandon its commitments to New Jersey is outrageous and calls into question the company’s credibility and competence. As recently as several weeks ago, the company made public statements regarding the viability and progress of the Ocean Wind 1 project. In recognition of the challenges inherent in large and complex projects, my Administration in partnership with legislative leadership insisted upon important protections that ensure New Jersey will receive $300 million to support the offshore wind sector should Orsted’s New Jersey projects fail to proceed. I have directed my Administration to review all legal rights and remedies and to take all necessary steps to ensure that Orsted fully and immediately honors its obligations.  

“Ultimately, as we have seen in other states recently, offshore wind projects awarded prior to 2020 have been impacted by a combination of interest rate escalation, supply chain cost increases, and inflation. And while today is a setback, the future of offshore wind in New Jersey remains strong. In recent weeks we’ve seen a historically high number of bids into New Jersey’s ongoing third offshore wind solicitation, and the Board of Public Utilities will shortly announce two additional solicitations related to our first-in-the-nation State Agreement Approach to build an offshore wind transmission infrastructure. 

“I remain committed to ensuring that New Jersey becomes a global leader in offshore wind – which is critical to our economic, environmental, and clean energy future.”

Govenor Phil Murphy stated Today’s decision by Orsted to abandon its commitments to New Jersey is outrageous and calls into question the company’s credibility and competence. Press Pool File photo Rich Hundley

Senate Minority Leader Anthony M. Bucco issued the following statement in response to Orsted announcing that they are withdrawing from New Jersey’s offshore wind project.

“Republicans stated for months that Orsted’s offshore wind project was unsustainable and would inevitably fail. Orsted’s decision today confirms that Republicans were right when we said this was too much, too fast, and too costly. Their financial challenges were glaringly obvious, yet Democrats ignored the warning signs to rush through Governor Murphy’s extreme energy master plan without any due diligence. This is just another example of how Governor Murphy’s outrageous energy master plan is coming back to hurt New Jersey taxpayers.

Thanks to the leadership of representatives like Congressman Jeff Van Drew and my Republican colleagues in the Legislature, the negative environmental and economic effects of Governor Murphy’s failed progressive offshore wind agenda were exposed. The public deserves to know how much money has been wasted on this epic boondoggle. Republicans stand ready to meet this challenge and to ensure that New Jersey’s energy portfolio is strong, safe, transparent, diverse, and fair. It’s time for Republican leadership.”

Senate Republicans warned over the summer that Orsted’s financial problems would pose a threat to the sustainability of their offshore wind projects. Orsted’s announcement today confirmed that Republicans were right.

Apr 28, 2022 Twitter Post:

Today, we announced an agreement with @Orsted to marshal New Jersey’s first offshore wind project with Ocean Wind 1. This partnership will:✅ Create good-paying jobs✅ Accelerate our clean energy goals

✅ Establish New Jersey a national leader in offshore wind pic.twitter.com/AYXuiIyU5s

— Governor Phil Murphy (@GovMurphy) April 28, 2022

31.10.2023 19:40

Today, Ørsted’s Board of Directors approved the interim report for the first nine months of 2023.

Operating profit (EBITDA) for the first nine months amounted to DKK 19.4 billion. Excluding new partnerships, EBITDA amounted to DKK 15.4 billion, DKK 1.0 billion higher than in the same period last year.

Earnings from offshore sites amounted to DKK 13.0 billion, which was DKK 6.8 billion higher than in the same period last year, and were positively affected by ramp-up at Hornsea 2 and Greater Changhua 1 and 2a and the negative impact from hedges in 2022 not being repeated.

Due to adverse impacts relating to supply chain delays, increased interest rates, and the lack of an OREC adjustment on Sunrise Wind, we have recognised impairment losses of DKK 28.4 billion in 9M 2023. The majority of these (DKK 19.9 billion) relates to our US offshore project Ocean Wind 1.

Net profit amounted to DKK -19.9 billion, and return on capital employed (ROCE) came in at -14 %. Net profit and ROCE excluding impairment losses amounted to DKK 8.5 billion and 13 %, respectively.

Our previously guided EBITDA for 2023, excluding new partnership agreements, of DKK 20-23 billion remains unchanged, when excluding a provision of approximately DKK 8-11 billion related to potential cancellation fees following our decision to cease the development of Ocean Wind 1. Due to a later timing across our project portfolio and the termination of investments on Ocean Wind 1, our gross investment for 2023 is now expected to amount to DKK 40-44 billion, a reduction of DKK 4 billion.

Mads Nipper, Group President and CEO of Ørsted, says in a comment to the interim financial report for the first nine months of 2023:
“We’re pleased with the performance of our operating assets in the first nine months of 2023, which drives a satisfactory development in our earnings. Our operating profit (EBITDA) excluding new partnerships increased by DKK 1 billion compared to the same period last year, and earnings from our offshore sites have more than doubled compared to last year.

“The current market situation with supply chain challenges, project delays, and rising interest rates has challenged our offshore projects in the US, and in particular our offshore project Ocean Wind 1, which has led to significant impairments in Q3 2023.

“Therefore, as part of our ongoing review of our US offshore wind portfolio, we’ve decided to cease the development of Ocean Wind 1 and Ocean Wind 2. At the same time, we’ve taken final investment decision on the 704 MW Revolution Wind project, progressing it to the construction phase with an attractive forward-looking value creation.

“Based on the challenged US portfolio and the current market conditions, we’ve initiated numerous actions to ensure our capital structure and rating and to improve our competitiveness and value creation.”

Financial key figures for 9M 2023:

DKK million Q3 2023 Q3 2022 % 9M 2023 9M 2022 %
EBITDA 9,173 12,317 (26 %) 19,403 25,361 (23 %)
– New partnerships 4,007 9,346 (57 %) 4,007 10,916 (63 %)
– EBITDA excl. new partnerships 5,166 2,971 74 % 15,396 14,445 7 %
Profit (loss) for the period (22,562) 9,355 n.a. (19,898) 15,325 n.a.
Cash flow from operating activities 9,796 (11,309) n.a. 22,362 (8,991) n.a.
Gross investments (9,204) (14,417) (36 %) (25,470) (27,621) (8 %)
Divestments 1,735 22,459 (92 %) (319) 24,653 n.a.
Free cash flow 2,327 (3,267) n.a. (3,427) (11,959) (71 %)
Net interest-bearing debt 42,892 45,701 (6 %) 42,892 45,701 (6 %)
FFO/adjusted net debt 20.9 % 35.3 % (14 %p) 20.9 % 35.3 % (14 %p)
ROCE (13.7 %) 24.4 % (38 %p) (13.7 %) 24.4 % (38 %p)

Earnings call
In connection with the presentation of the interim report for the first nine months of the year, an earnings call for investors and analysts will be held on Wednesday, 1 November 2023 at 14:00 CET.

Denmark: +45 78 76 84 90International: +44 203 769 6819

USA: +1 646 787 0157 

PIN: 994005

The earnings call can be followed live at: 
Ørsted | Interim report for the first nine months of 2023 (eventcdn.net)  

Presentation slides will be available prior to the earnings call at:
Investors | Ørsted (orsted.com)

The interim report is available for download at:
https://orsted.com/financial-reports

Save LBI: “Promises and Realities -Wind Turbine Projects Off LBI Shores”

Are New Jersey’s Windmill Projects Killing The Whales?

« Matawan Acupuncture Doctor Charged with Sexual Assault of Patient – MidJersey.News » Rep. Smith’s Bill To Combat Anti-Semitism Becomes Law – MidJersey.News

Recent Posts

  • Esports sur 1xBet Mobile : Disciplines Couvertes, Marches et Streaming Integre
  • MidJersey.News – From the Delaware River to the Jersey Shore
  • SpaceX Falcon 9 Rocket Launch as Seen From New Jersey – MidJersey.News
  • Election Problems Reported In Mercer County, NJ – MidJersey.News
  • Governor Murphy Visits Trenton’s “Real Time Crime Center” – MidJersey.News

Recent Comments

No comments to show.

Archives

  • May 2026
  • September 2025
  • August 2025
  • July 2025
  • June 2025
  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020

Categories

  • News
  • paris-sportifs

↑

© reviewthickandthin.com 2026
Powered by WordPress • Themify WordPress Themes